A PROJECT MANAGER WANTS TO HAVE SOME OF THE PEOPLE TRAINED ON HISP...

28. A project manager wants to have some of the people trained on his

project team. The project team is working in a balanced matrix organi-

zation. Generally, the approval for this training should come from

which of the following managers?

a. Project manager

b. Executive manager

c. Functional manager

d. Human resources manager