A PROJECT MANAGER IS MANAGING A PROJECT. THE ORIGINAL SCOPE BASELI...

28. A project manager is managing a project. The original scope baseline ofthe project was budgeted at $100,000. Since work on the project startedthere have been seventeen authorized and approved changes to the proj-ect. The changes have a value of $17,000 and the cost of investigatingthem prior to their approval was $2,500. What is the current budgetfor the project?a. $100,000b. $114,500c. $117,000d. $119,500