A PROJECT MANAGER WANTS TO SUBCONTRACT PART OF THE PROJECT. THIS P...

14. A project manager wants to subcontract part of the project. This part

of the project is quite complicated, and there are many ways that the

work can be done. What method of solicitation should be used by the

project team?

a. Request for bid

b. Request for quotation

c. Request for proposal

d. Request for information