12 TESTS AFTER COMPLETION IN THE YELLOW AND SILVER BOOKS, PROVISION...
In the Yellow and Silver Books, provision is made in clause 12 for testing after
completion; but this clause only applies if such tests are specifically stated in
the contract. They tend to be provided for in projects where the complexity of
the plant or facilty or the technology used make it important to provide for
further testing after Taking Over. These tests often involve an extended trial
operation.
The tests are to be carried out as soon as reasonably practicable after the
works or section have been taken over by the Employer. The Contractor is
entitled to 21 days ’ notice of the date after which the tests after completion will
be carried out. Unless otherwise agreed, the tests shall be carried out within 14
days after this date, on the day or days determined by the Employer or Engineer.