4.12 Tests after completion

In the Yellow and Silver Books, provision is made in clause 12 for testing after

completion; but this clause only applies if such tests are specifically stated in

the contract. They tend to be provided for in projects where the complexity of

the plant or facilty or the technology used make it important to provide for

further testing after Taking Over. These tests often involve an extended trial

operation.

The tests are to be carried out as soon as reasonably practicable after the

works or section have been taken over by the Employer. The Contractor is

entitled to 21 days ’ notice of the date after which the tests after completion will

be carried out. Unless otherwise agreed, the tests shall be carried out within 14

days after this date, on the day or days determined by the Employer or Engineer.