4 THE CONTRACTS CONTAIN DETAILED PROVISION WITH REGARD TO TESTING THE QUALITY AND PERFORMANCE OF THE WORKS AND ANY PART OF THEM
The contracts contain detailed provision with regard to testing the quality and
performance of the works and any part of them.
Clause 7.4 provides for requirements concerning testing that apply to all
tests specified in the contract other than the tests after completion (if any): see
further Sections 4.9 and 4.12 below.
The Contractor is to provide everything necessary to carry out the tests
specified, unless otherwise stated in the contract. He is to agree with the
Engineer or Employer the time and place for the specified testing.
The Engineer or Employer may vary the location or details of specified tests,
or instruct the Contractor to carry out additional tests. If these varied or
additional tests show that the item is not in accordance with the contract, the
additional or varied tests are to be carried out again at the Contractor ’ s expense.
The Engineer or Employer must give the Contractor not less than 24 hours ’
notice of his intention to attend the tests. If he does not attend at the time and
place agreed, the Contractor may proceed with the tests unless otherwise
instructed by the Engineer or Employer, and the tests shall be deemed to have
been made in his presence and to be accurate.