IF A PROJECT MANAGER WERE TO MAKE THANKSGIVING DINNER, TWO OF THEA...

11. If a project manager were to make Thanksgiving dinner, two of the

activities that might be of concern would be roasting the turkey and

baking the sweet potatoes. In order to ensure that these two items will

be finished cooking and will come out of the oven at the same time,

what type of relationship should he or she use in the schedule between

these two activities?

a. Finish-finish

b. Start-start

c. Finish-start

d. Start-finish