BIT IS GENERALLY ACCEPTED THAT FOR MOST PROJECTS, ONCE A PROJECT’S DEF...

30. Answer: b

It is generally accepted that for most projects, once a project’s definitive esti-

mate has been completed, the actual project cost will be not more than 5%

below the definitive estimate and not more than 10% above it.