WHEN USING PERT ANALYSIS ON A PROJECT SCHEDULE, PROBABILISTIC OR E...

31. When using PERT analysis on a project schedule, probabilistic or ex-pected durations are used for activity durations. If there is a concernthat the critical path may shift due to durations changing within theexpected range, what technique can be used?a. CPMb. Monte Carloc. Decision treesd. Finite element analysis