11.4 FURTHER TESTS
4.11.4 Further tests: Clause 11.6
If the work of rectifying any defects may have affected the performance of the
works, the Engineer or Employer may require a repetition of any test required
under the contract within 28 days after the remedying of the defect or dam-
age. The cost of performing repeated tests is to be borne by the party liable for
the cost of rectifying the defects.