QUESTIONS 12 THROUGH 15 REFER TO THE DIAGRAM IN FIGURE 2 AND THE TABLE...
TÀI LIỆU PROJECT MANAGEMENT PROFESSIONAL CHAPTER 12A QUESTION DOCX
Nội dung
Đáp án tham khảo
15. What is the standard deviation for the duration of activity B?
a. 1.000
b. .133
c. .166
d. 1.413
Bạn đang xem
15.
-