19. Schedules are used in many ways. In a project to build a bridge the
project manager wants to use a tool that will show the scheduled activi-
ties in such a way that it is easy to see when each activity starts and
finishes and which activities are taking place at the same time. Which
tool should be used?
a. PERT chart
b. Gantt chart
c. Precedence diagram
d. GERT chart