6.1 UNFORESEEABLE PHYSICAL CONDITIONS IN THE SILVER BOOK, THE CONTRA...

2.6.1 Unforeseeable physical conditions

In the Silver Book, the contractor bears the risk of unforeseen difficulties

unless this is otherwise stated in the contract. By clause 4.12, unless the con-

tract states otherwise:

the contractor is to be taken to have obtained all necessary information as

to risks, contingencies and other circumstances which may influence or

affect the works;

by signing the contract the contractor accepts total responsibility for having

foreseen all difficulties and costs of successfully completing the works; and

the contract price is not to be adjusted to take account of any unforeseen

difficulties or costs.

The risk borne by the contractor here is therefore total, unless the contract

(by the particular conditions) expressly permits an additional payment.

Equally, the contractor is not permitted an extension to the contract comple-

tion date if he encounters physical difficulties (clause 8.4). By contrast, under

clause 4.12 of the Yellow and Red Books, the contractor could obtain an

extension of time and additional payment (cost but not profit) if he encoun-

ters physical conditions which were unforeseeable in the sense  that  no

experienced contractor at the date of tender could reasonably be expected to

have foreseen them. He is also permitted an extension of time by clause 8.4.