ONE OF THE TASKS THAT THE PERSON IN THE ABOVE PROJECT IS ASSIGNED...

31. One of the tasks that the person in the above project is assigned requires100 hours of effort. What is the cost of the task?

... 9618$$

CH13

09-06-02 15:00:26

PS

a. $12,187b. $16,927c. $9,750d. 13,541