22. A task was scheduled to use two persons, full time, and take two weeks
to complete. Instead, the project manager was only able to assign one
person to this task. At the end of two weeks, the person assigned to the
task was 75% complete. What is the cost performance index?
a. .75
b. 1.5
c. 1.33
d. .5