QUESTIONS 12 THROUGH 15 REFER TO THE DIAGRAM IN FIGURE 2 AND THE TABLE...

22. A task was scheduled to use two persons, full time, and take two weeks

to complete. Instead, the project manager was only able to assign one

person to this task. At the end of two weeks, the person assigned to the

task was 75% complete. What is the cost performance index?

a. .75

b. 1.5

c. 1.33

d. .5