QUESTIONS 12 THROUGH 15 REFER TO THE DIAGRAM IN FIGURE 2 AND THE TABLE...

18. The original schedule (for a project, a work package, or an activity),

plus or minus approved changes, is called:

a. The working schedule.

b. The target schedule.

c. The performance schedule.

d. The baseline schedule.