1 THE CONTRACTOR ’ S GENERAL OBLIGATION

4.4.1 The Contractor ’ s general obligation: Clause 4.1

In both Books, the Contractor is to:

design, execute and complete the works in accordance with the contract,

and

remedy any defects in the works, so that

when completed, the works shall be fit for the purposes for which the

works are intended as defined in the contract.

An important feature of this general obligation is the requirement to

complete the works so that they are ‘

fit for the purposes ’ for which they are

intended ‘

as defined in the contract ’. The Contractor under such a fitness for

purpose obligation is in principle liable even if he took reasonable care in, for

example, the design of the facility if the end product does not achieve the

purposes for which it was intended.

But how are these intended purposes to be assessed? In the FIDIC Books

this is by reference to the terms of the contract: the works are to achieve the

purposes

defined in the contract ; these definitions are to anchor the intended

purposes which the end product must achieve. This places a lot of weight,

therefore, on the contract documents specifying the intended purposes suffi-

ciently clearly and adequately; but care needs to be taken to avoid doing so too

narrowly or too broadly for the design-build contractor to do his job and be

responsible for the end result.

Note also that ‘defined’ is not the same as

express : an intended purpose for

some part of the plant or facility (light fittings, for example) could be implied

or to be inferred from the descriptions of the items used rather than expressly

stipulated.

Whether the works or some part of them is ‘fit for the intended purpose’

may not always be clear. Take, for example, a contractor who is to design and

constructs a spa hotel in a seaside resort. The site directly faces the open sea.

The Employer ’ s Requirements specify ‘

steel frame windows ’ of certain dimen-

sions ‘

for all sea-facing windows ’.

Within the fixed price the contractor supplies and installs carbon steel

frames with a much lower corrosion resistance than inox or chromium-alloy

steel. However, following installation the employer requires that the win-

dows be replaced with inox frames, on the basis that carbon steel frames are

not fit for the purpose. The employer contends that, in the sea-facing posi-

tion, they will corrode at more than three times the rate of chromium-alloy

steel of median grade.

We can sympathise with the employer, but is he right? The contractor, after

all, might reply that the Employer ’ s Requirements did not include any particu-

lar type or grade of steel and no service life was (let us assume) ever specified.

He could say he was entitled to design for the less expensive carbon steel solu-

tion and was not in breach of any contract terms. In a case like this there are

arguments which could be adduced on either side. Can the contractor be

required, he might ask, to install more expensive materials within the lump-

sum fixed price even if they were never specified? Or any performance stand-

ard in terms of service life ever stated?

The words of clause 4.1 are ‘…

for which the Works are intended as defined in

the Contract ’. But what was the intended purpose as defined in the contract?

Could one say that the contract at least implicitly defined the intended pur-

pose as ‘use of frames to windows directly facing the sea’, as the plans and site

details showed the location? Or could one argue persuasively that in the

absence of any express service life requirement the need to replace the carbon

steel frames more frequently than chromium-alloy frames is at bottom a

maintenance issue and not one about fitness for purpose?

Again arguments could be adduced on both sides. The employer here

would certainly be helped by the fact that an intended purpose might be

implied or implicit; but to avoid arguments of this kind the Employer ’ s

Requirements, or other contract documents, should have been more explicit

on the point if (as it evidently was) it was an important one.