A PROJECT TEAM RECEIVES AN APPROVED CHANGE REQUEST FROM THE CUSTOME...

8. A project team receives an approved change request from the customer.The team has previously estimated that the cost to implement thischange is $10,000. The customer has agreed to pay this amount for theadditional work. The customer realizes that there is a 50 percent chancethat this change will not work and will later be removed. What change,if any, should be made in the budget?a. The project budget should not be increased.b. The project budget should be increased by $15,000.c. The project budget should be increased by $10,000.d. The project budget should be increased by $5,000.