THE PROJECT TEAM HAS DELIVERED A DELIVERABLE TO THE CUSTOMER. THE...

11. The project team has delivered a deliverable to the customer. The deliv-

erable contains defects that are easily correctable. There is a good rela-

tionship with the customer and the customer agrees to make the repairs

and correct the defects on the item and invoice the supplier for the

work that was done. This is considered to be a:

a. Bid cost reduction.

b. Payment authorization.

c. Back charge.

d. Release payment.