27. Answer: c
The request and agreement to a specific date for completion of a particular
milestone in the project is called a constraint. Constraints for project tasks and
activities that do not put them on the critical path are not necessarily a problem
as long as delays in the schedule do not ultimately place them on the critical
path. Some process constraints may be predefined as constraints. For example,
management may specify a target completion date rather than allowing it to be
determined by the planning process. Constraints are factors that will limit the
project management team’s options. For example, a predefined budget is a con-
straint that is highly likely to limit the team’s options regarding scope, staffing,
and schedule.