27. A project is proposed to a customer. Price and schedule for delivery areagreed upon. The work breakdown structure is agreed to as well. Thecustomer requests that one of the milestones of the project be completedby a certain date. The project schedule is reviewed, and it is found thatthe expected completion date for this milestone is considerably earlierthan the date requested by the customer. The date for this milestone iswhich of the following?a. Considerationb. Summary activityc. Constraintd. Suggestion