DMOST OF THE PROJECT MONEY WILL BE SPENT DURING THE EXECUTION PHASE. A...

8. Answer: d

Most of the project money will be spent during the execution phase. At the

beginning of execution the rate of expenditures rises as people and materials are

brought into the project. Later the expenditures peak and slow down. By the

end of the execution phase expenditures are approaching a minimum.