4.8.1 Commencement and time for completion of the works: Clauses 8.1 and 8.2
Clause 8.1 of the Books provides for the
contract commencement date to be
notified to the Contractor by the Engineer or Employer at least 7 days prior
to the commencement date, and (unless otherwise stated in the contract)
for that date to be within 42 days of the date when the contract came
into effect.
7
The Contractor as soon as reasonably practicable after the commencement
date must proceed with the design and execution of the works and, by clause