2.3 EMPLOYER ’ S CLAIMS AGAINST THE CONTRACTOR

4.2.3 Employer ’ s claims against the Contractor: Clause 2.5

One naturally thinks of the Contractor as making claims, for an additional

payment, say, or more time to complete the contract works. But the Employer

too can claim; and under the contract these claims will be either for a payment

of some kind (damages for delay, for example, or sums due pursuant to a right

of indemnity, such as we saw in connection with clause 1.13 above) or for an

extension to the defects notification period under the contract (see Section