3.4 THE GIVING OF INSTRUCTIONS ONE SPECIFIC FUNCTION OF THE ENGINEER...
4.3.4 The giving of instructions
One specific function of the Engineer under the Yellow Book (or those to
whom he has delegated the power to do so) is the general right to give instruc-
tions (which are to be in writing) to the Contractor, at any time, which are
necessary either for the execution of the works or for the remedying of any
defects in them (clause 3.3). Instructions amounting to a variation to the
works are to be treated as such under clause 13 (see Section 4.13 below).
In the Silver Book, clause 3.4, there is a similar right in the Employer to give
instructions, expressed as the right to issue instructions (in writing) to the
Contractor which may be necessary for the Contractor to perform his obliga-
tions under the contract.