A PROJECT MANAGER IS USING THE EARNED VALUE REPORTING SYSTEM TO MA...

37. A project manager is using the earned value reporting system to managehis project. At this point in time the EV is $24,000, the BAC is$97,000, the PV is $29,000, and the AC is $45,000. What is the per-cent complete?a. 30%b. 25%c. 46%d. 53%