A PROJECT MANAGER AND THE PROJECT TEAM IDENTIFY SEVERAL SPECIFIC RI...

4. A project manager and the project team identify several specific risks ina project. The expected value of these risks is estimated at $10,000. The

255

impact on the project brought about by these risks is estimated at$40,000. What value should be entered into the management reservefor these risks?a. $10,000b. $40,000c. $0d. $25,000