YOU ARE MANAGING A PROJECT AND THE CUSTOMER’S ENGINEERS VISIT YOURF...
8. You are managing a project and the customer’s engineers visit your
facility on an inspection and general getting acquainted tour. During
the tour they make the comment that the parts that are being designed
should be in stainless steel instead of plain steel with enamel. What
should you do?
a. Authorize the change in design to your engineers.
b. Continue with the present design.
c. Speak to the visiting engineers and discuss having an informal meet-
ing between your engineers and the visiting engineers.
d. Ask the visiting engineers to submit a change proposal to the change
system.