4 ESTIMATE THE EFFORT TO DEVELOP THE ABOVE SYSTEM, ASSUMING 6 SCREE...

30.4 Estimate the effort to develop the above system, assuming 6 screens,4 database tables, 2 reports, no interfaces to other systems, 1 personmonth per function point, no software reuse, a difficulty factor of 1.5because it is a web-based solution.