WHICH OF THE FOLLOWING CHOICES WOULD BE AN ACCEPTABLE CAUSE FOR ‘‘...

10. Which of the following choices would be an acceptable cause for ‘‘re-baselining’’ a $10 million project?a. The monthly consumer price index on some of the commoditiesused on the project have been identified as having gone up by 1.6%,an increase of 46% over the 1.1% which had been budgeted.b. The client has authorized a $10,000 addition to the scope of theproject.c. The contractor’s company has instituted a quality program on whichthey have pledged to spend $1 million during the next year.d. The productivity in the drafting department has shown to be lowerthan anticipated, which has resulted in 1,000 additional hours, a78% increase over what was budgeted.