THE TIME PHASED COST OF THE PROJECT THAT REFLECTS THE EXPENDITURES...

12. The time phased cost of the project that reflects the expenditures ratherthan the consumption of a resource that will be used to measure andmonitor cost performance on a project is the:a. Spending plan.b. Cost baseline.c. WBS.d. Schedule.