EXERCISE 8-21 (CONTINUED)

3. The costs of each of the jobs can be computed as follows using the activity rates computed above:

a. Routine one thousand square feet job:

Job size (1 thousand square feet @ $970 per thousand square feet)... $ 970.00

Estimating and job setup (1 job @ $239 per job)... 239.00

Nonroutine job (not applicable)... 0

Total cost of the job... $1,209.00

Cost per thousand square feet ($1,209 ÷ 1 thousand square feet)... $1,209.00

b. Routine two thousand square feet job:

Job size (2 thousand square feet @ $970 per thousand square feet)... $1,940.00

Total cost of the job... $2,179.00

Cost per thousand square feet ($2,179 ÷ 2 thousand square feet)... $1,089.50

c. Nonroutine two thousand square feet job:

Nonroutine job ... 6,430.00

Total cost of the job... $8,609.00

Cost per thousand square feet ($8,609 ÷ 2 thousand square feet)... $4,304.50

Problem 8-27 (continued)