48. (Note: If either party is prevented from, or delayed in, performing any duty under this
Contract by an event beyond his reasonable control, then this event shall be deemed
force majeure.)
Shortage of supplies (Background: The exporter cannot get the raw jute he needs from
the supplier because the Central Bank will not give him foreign exchange to pay the
supplier)
A. Yes
B. Questionable
C. No