230. CSO: 1C4c LOS: 1C4j
When demand for a product or products exceeds production capacity, which one of the
following is the first step that managers should take?
a. Spend money to eliminate the bottleneck.
b. Focus their efforts on constraint identification.
c. Change the throughput of operations.
d. Apply activity-based management to solve the problem.