EVEN IF ESTIMATED NPV FOR A PROPOSED PROJECT FOR THE PARENT IS DIF...

61. Even if estimated NPV for a proposed project for the parent is different from estimated NPV for the subsidiary, a project that shows ____________________________ should probably be pursued. a. NPV<0 for the parent and NPV<0 for the subsidiary b. NPV>0 for the parent and NPV<0 for the subsidiary c. NPV<0 for the parent and NPV>0 for the subsidiary. d. NPV>0 for the parent and NPV>0 for the subsidiary