11-7 The overhead efficiency variance does
a single level of activity that remains unchanged
not really measure efficiency in the use of over-
head. It actually measures efficiency in the use
even if the activity level subsequently changes.
of the base underlying the flexible budget. This
base could be direct labor-hours, machine-
Bạn đang xem 11- - SOLUTIONS TO QUESTION MANAGERIAL ACCOUNTING CH11 FLEXIBLE BUDGETS AND OVERHEAD ANALYSIS