UNIT 8 $6,860 ($9,800 X .70) COST OF NEXT 7 UNITS = (8 X $6,860...

85. Correct answer b. A static budget is based on the level of output planned at the start of the

budget period and does not change no matter what the level of actual output. Comparison

of actual activities to static budget levels is difficult and often misleading.