CORRECT ANSWER C. THE PAYBACK PERIOD FOR FOSTER’S PROJECT IS 3....
346.
Correct answer c. The payback period for Foster’s project is 3.0 years ($20,000 - $6,000 -
$6,000 - $8,000 = 0).