EXERCISE 10-15 (CONTINUED) ALTERNATIVE SOLUTION
EXERCISE 10-15 (CONTINUED) ALTERNATIVE SOLUTION
SOLUTIONS TO QUESTION MANAGERIAL ACCOUNTING CH10 STANDARD COST AND THE BALANCE SCORECARD
Nội dung
Đáp án tham khảo
6,400 hours ($2.75 per hour – $2.50 per hour) = $1,600 U Variable overhead efficiency variance = SR (AH – SH) $2.50 per hour (6,400 hours – 7,200 hours) = $2,000 F