141. Correct answer d. As long as the project return is above the cost of capital, the manager of
the Construction Equipment Division will accept the project. The manager of the
Household Appliances Division, measured on the basis of ROI, will not accept a projected
rate of return of 14% when the current ROI of the division is 16%.