1 (10 MINUTES) A. PROCESS COSTING G. JOB-ORDER COSTING B. J...

Exercise 3-1 (10 minutes)

a. Process costing g. Job-order costing

b. Job-order costing h. Process costing*

c. Process costing i. Job-order costing

d. Process costing j. Process costing*

e. Process costing k. Job-order costing

f. Job-order costing l. Job-order costing

* Some of the companies listed might use either a job-order or a process

costing system, depending on how operations are carried out. For ex-

ample, a chemical manufacturer would typically operate with a process

costing system, but a job-order costing system might be used if prod-

ucts are manufactured in relatively small batches. The same thing might

be true of the tire manufacturing plant in item “j.”

© The McGraw-Hill Companies, Inc., 2006. All rights reserved.