7 . If activity-based costing is implemented in an organization without any other changes
being effected, total overhead costs will
a. be reduced because of the elimination of non-value-added activities.
b. be reduced because organizational costs will not be assigned to products or services.
c. be increased because of the need for additional people to gather information on cost
drivers and cost pools.
d. remain constant and simply be spread over products differently.