DURING WEEK 5 IT IS FOUND THAT SOME OF THE WORK THAT WAS REPORTEDC...

19. During week 5 it is found that some of the work that was reportedcomplete in week 2 was considered unacceptable. It will require $500to fix the problem and make this work acceptable. The work is sched-uled to be done in week 6. No other work is reported to be completeduring week 5. What is the EV for week 5?a. 7,000b. 6,500c. 9,000d. 5,000