UNIT 8 $6,860 ($9,800 X .70) COST OF NEXT 7 UNITS = (8 X $6,860...

212. Correct answer c. The overhead applied to a job incurring 20 hours of direct labor is $140

as shown below.

Total budgeted direct labor hours: $50,000 ÷ $5 = 10,000 hrs.

Overhead cost/direct labor hour: $70,000 ÷ 10,000 = $7 per hr.

Overhead cost for 20 hours: 20 x $7 = $140