UNIT 8 5,120 HRS. (6,400 X .80) 98 98

27. Correct answer a. Batch 1 = 800 ÷ 4 units = 200 per unit

Batch 2 = (800 x .9) ÷ 4 units = 180 per unit

Batch 4 = (1,440 x .9) ÷ 8 units = 162 per unit

Hours for next 12 units = (16 x 162) - 800 for first 4 units

= 2,592 - 800

= 1,792 hours