27. The overall duration of the project schedule is not influenced by:
a. Using mandatory dependencies as constraints.
b. Using discretionary dependencies as constraints.
c. The availability of the resources that are assigned to perform the
work.
d. Using the arrow diagramming method instead of the precedence
diagramming method (PDM) of scheduling.