QUESTIONS 12 THROUGH 15 REFER TO THE DIAGRAM IN FIGURE 2 AND THE TABLE...

26. The project schedule is not used to determine:

a. The start and finish dates of the activities.

b. Occasional changes to the activity listing.

c. The total float of the activities.

d. The project’s budget.