QUESTIONS 12 THROUGH 15 REFER TO THE DIAGRAM IN FIGURE 2 AND THE TABLE...

37. A project manager would like to manage his project in such a way that

he will be able to predict more accurately the duration of the project

even though the estimates for the duration of the activities have a lot

of variability. The project manager should use which method to more

accurately predict the project completion date?

a. CPM

b. GERT

c. PERT

d. Activity sampling